An American data-centre giant walked away from a field outside Zaragoza. A few weeks later, the Sultanate of Oman walked in, with seven billion euros on the table.
That is how this week went. Money is chasing anything that makes a data centre work: the power, the batteries that hold it, the land, the people who wire the buildings, and the banks willing to lend against all of it.
Grid and power
Before a data centre can run a single computer, someone has to bring it electricity. This week that someone came in very different shapes.
Paraguay and its dam
Paraguay · Power for data centres
Itaipú is one of the largest hydroelectric dams in the world, shared by Paraguay and Brazil. Crusoe, founded in Denver in 2018 to turn oilfield gas flares into electricity, now calls itself "the AI factory company". It builds data centres where cheap power already exists, instead of waiting for the grid to come to it. Crusoe has teamed up with Araico, a Paraguayan energy and infrastructure developer, to build AI data centres running on Itaipú's power. The first site should open by mid-2027 at 106 megawatts, with room to grow to about 280. The US Deputy Secretary of State was in Asunción for the announcement.
The open question: Paraguay's state utility, ANDE, has not said a word about the power contract. Countries with surplus clean power and no big industry to use it may be the next stage for AI.
America and its gas
United States · Gas pipelines
Kinder Morgan is one of the biggest pipeline operators in the United States. It approved $4.7 billion of new pipelines: $3.1 billion for the Southeast Connector and $1.6 billion for the Permian Link. Gas is what many US data centres will burn while they wait for cleaner power.
The US government and its wires
United States · Grid
The US Department of Energy put $5.25 billion, $1.9 billion federal and the rest from utilities, into 31 grid projects across 26 states. Most of it goes to replacing old power lines with ones that carry more electricity on the same route. That is faster than building new lines, which can take a decade to get permits.
Hornsea 3: Britain sells the link to the shore
UK · Offshore transmission
On October 21 Ofgem, Britain's energy regulator, launched its largest tender yet for offshore transmission: the cables and substations, worth around £3.5 billion, that connect the Hornsea 3 wind farm to the grid. Hornsea 3 sits more than 100 km out in the North Sea, is due for completion by the end of 2027 and is expected to power 3.3 million homes. The winner gets an inflation-linked income for up to 25 years to own, run and maintain the link, as long as it stays available. Since 2009, winning bidders have invested more than £10 billion in links to 28 offshore wind farms.
Analysis: this is one of the few ways for long-term investors to buy finished grid assets with a regulated, inflation-linked income.
Power cables under European seas
Spain · UK · Subsea power
Nexans, the French cable maker, was chosen to design a second power cable between Mallorca and Menorca for Red Eléctrica, Spain's grid operator. In Scotland, SSE picked Seaway7, part of Subsea7, to install the foundations and cables for its 1.4-gigawatt Berwick Bank B offshore wind farm.
Sources: UPI, ABC Color, Contrary Research on Crusoe, Journal Record, EconoTimes, MarineLink, Ofgem
Batteries and storage
A few years ago, banks treated big batteries as a gamble. This week they lent against them the way they lend against a wind farm.
Hams Hall, by the numbers
UK · Batteries
BW ESS secured loans for Hams Hall, a 350-megawatt battery in the English Midlands that can store 1,243 megawatt-hours, roughly three and a half hours of full output. OCBC, Rabobank and Société Générale lent equal shares. The Deal Radar covers why the banks said yes: a ten-year income floor from EDF. In Spain the same logic financed BRUC and Alter Enersun's €222 million of solar-plus-battery sites (details).
Nefer Menya, Egypt
Egypt · Solar and batteries
The EBRD, the European development bank, arranged up to $265 million for Nefer Menya, a 1.2-gigawatt solar and battery project in Egypt.
Sources: Solar Power Portal, Watson Farley & Williams, fundsforNGOs
Data centres
Zaragoza: local owners take money straight from Oman
Spain · Gulf · Data centres
Vantage Data Centers, a large American developer, had announced a campus near Zaragoza in 2025, then pulled out. In its place a group of local Aragonese businessmen formed a company called Copiapo. It is led by Pedro Machín of Atalaya, a wind-energy company; Reynaldo Benito of Posidonia, which builds industrial parks, and who is also president of the Zaragoza basketball club; and Jesús Garcés of Tecnyconta. Their partner is O-Green, an investment vehicle linked to the Oman Investment Authority, Oman's sovereign wealth fund.
Together they plan a 570-megawatt campus on 122 hectares in San Mateo de Gállego, built in four phases over ten years. The first investment is €1.2 billion. It could grow to €7.4 billion if enough power can be found.
What it means: this is not a big American operator. It is local landowners and energy people who own the land and the grid position, taking money directly from a Gulf state.
IREN in Badajoz
Spain · Data centres
On the other side of Spain, near the Portuguese border, IREN, an AI cloud company listed on Nasdaq, set up IREN Europe and got its construction licence for a 300-megawatt campus, opening in 2028. Its pitch: European companies that want their AI to run inside Europe. It has no announced customers and no financing yet.
So for Spain: in one week, Gulf money arrived in Aragon, an American cloud company planted a flag in Extremadura, and Spanish banks lent against batteries. Spain has the sun and the land. What it has lacked is a way to make that power reliable and someone willing to fund it. This week both started to show up.
Ankara Temelli
Turkey · Data centres
Rönesans and Digital Realty broke ground on the Ankara Temelli campus in the Başkent industrial zone. The full plan is $4.1 billion over three phases; the first phase is $450 million and more than 22 megawatts, opening in 2028, for government agencies, banks and tech companies. A global operator brings the customers and the know-how, a local builder brings the land, the permits and the political relationships. It is the same shape as Zaragoza. Who the two companies are, and the Rönesans Altyapı listing plan: Deal Radar.
Polar in Tørdal
Norway · Data centres
Polar, the London-based developer controlled by H.I.G., already runs a 12-megawatt building in Tørdal, Norway, for Crusoe. It is adding 40 megawatts more, liquid-cooled and powered by hydroelectricity, opening in late 2027.
Soluna and Applied Digital in Texas
United States · Data centres
Soluna is a small US company that builds data centres next to wind farms. Applied Digital is a larger, Nasdaq-listed data-centre developer. They formed a joint venture for a 50-megawatt AI site near Silverton, Texas, fed by Soluna's own 150-megawatt wind farm.
SK Telecom
South Korea · Data centres
SK Telecom is South Korea's largest mobile operator, part of the SK Group. Its data-centre arm, SK Hyper, says it needs $350 billion just for the first 5 gigawatts of a 15-gigawatt plan. Its CEO, Chung Suk-geun, is talking to big tech firms and investors. A phone company is turning itself into a power-and-data-centre company.
Chief Telecom
Taiwan · Data centres
Chief Telecom is part of Chunghwa Telecom, Taiwan's main telecom operator. It runs internet exchanges and subsea cable connections. It broke ground on a 16-megawatt AI data centre in Huwei, central Taiwan, a NT$3.3 billion investment opening in 2028. It is the same move as SK on a smaller scale: a telco using its cables and connections to sell computing power.
Sources: Heraldo, El Periódico de Aragón, elEconomista, IREN, 24/7 Wall St, IDC Nova, Yeni Şafak, GlobeNewswire via Yahoo, ETDatacenters, Business Times, TechNews
Towers, fibre and cables
Zain and Ooredoo close the first phase of their tower venture
Gulf · Towers
Kuwait's Zain Group and Qatar's Ooredoo closed the first phase of their 50/50 tower joint venture on October 23. It combines about 4,000 towers in Kuwait and Qatar. When it was announced nearly three years ago, the venture was reported at $2.2 billion and expected to reach about 30,000 towers across the Middle East and North Africa. More portfolios will be added as approvals come through.
What it means: Gulf operators are separating their towers from their networks, as European operators did. That creates a regional tower platform that can raise its own money.
Korda: Iceland puts its cables under one roof
Iceland · Subsea cables
Farice, which runs Iceland's international subsea cables, has merged with the telecom arm of Neyðarlínan, the national emergency line, and Öryggisfjarskipti, the security communications company. The merger was completed in early October and the combined company now operates as Korda. It runs the IRIS, DANICE and FARICE-1 cables and the national Tetra emergency radio network, and is preparing a fourth cable, AUÐI.
What it means: a small country is putting its international links and its emergency network in one company, which makes it easier to plan and finance the next cable.
When regulators say no
UK · Italy · Fibre
In Britain, nexfibre, a fibre company backed by Liberty Global and Telefónica, wanted to buy its smaller rival Netomnia for £2 billion. The competition regulator objected, and nexfibre's owners refused to offer concessions. The deal now looks dead. In Italy, the European Commission formally accused KKR, the American private equity firm, of giving misleading information when it bought Netco, Telecom Italia's fixed network.
What it means: when the big fibre mergers are blocked, the smaller fibre companies get bought one at a time instead.
The builders and crews
Behind every data centre and every cable there are crews and equipment. This week those crews became targets.
CBRE and Onnec
UK · Data centre services
CBRE, the world's largest commercial real estate company, agreed to buy Onnec, the London company that has been installing fibre, cabling and networks inside buildings since 1986 and now works in data centres for the biggest tech firms. The price is about £460 million upfront, plus up to £300 million more if Onnec hits targets. A real estate giant is paying that much for the people who wire the building, not the building itself. More on the deal: Deal Radar.
Ember and Ashtead
UK · Subsea services
Ashtead Technology, from Aberdeen, Scotland, was founded in 1985 and has more than 520 people. It rents and runs the equipment used to install, inspect and repair things under the sea, from offshore wind to cables. Ember Infrastructure, a New York private equity firm, offered £505 million, 615 pence a share, and Ashtead's board recommended it. It should close around the end of the year.
What it means: the tools that keep subsea infrastructure running are now an investment in their own right.
Sources: CBRE, Wrenews, Ashurst, Perkins Coie, Ashtead Technology
Capital: who is paying
Nebius and Citi
Netherlands · AI cloud finance
Nebius is an AI cloud company based in Amsterdam and listed on Nasdaq. It was the Dutch parent of Yandex until it sold the Russian business in 2024 and took its new name; it runs its own data centre in Mäntsälä, Finland. It borrowed $3.5 billion from Citi, for one year, secured against customer contracts it has already signed. Instead of selling more shares or convertible bonds, it is borrowing against its order book.
Crusoe, twice
United States · Gulf · AI infrastructure finance
Crusoe raised $1.375 billion at a valuation above $10 billion, co-led by Mubadala, an Abu Dhabi state investor, and Valor Equity Partners. Separately, Neuberger, the New York asset manager, gave Crusoe a $700 million facility just to buy power generators. Generators are now financed on their own, the way airlines finance planes.
Pension funds and ports
UK · Ports
Associated British Ports is the UK's largest port group and handles about a quarter of Britain's sea trade. Its owners, two Canadian pension funds, CPP Investments and OMERS, agreed to sell their 63.88% stake to IFM Investors, a fund owned by Australian pension funds. The deal values ABP at more than £10 billion. Retirement money from one side of the world is handing a British port group to retirement money from the other.
The World Bank in Asia
Asia-Pacific · Infrastructure funds
IFC, the World Bank's private-sector arm, is weighing up to $150 million for a new Asia-Pacific infrastructure fund run by Macquarie, the Australian infrastructure investor. The fund targets data centres, fibre and renewables, including in the Philippines.
Sources: Nebius, RTTNews, Nebius Group (Wikipedia), Crusoe, Worldnews, ShipUniverse, Bloomberg, BusinessWorld
The bottom line
Follow the chain: power, then batteries, then buildings, then the crews, then the money. At every link this week, the money came from sovereign funds, pension funds and private equity. And in Zaragoza, Ankara and Paraguay, the winners were not the global giants. They were the local partners who owned the land, the power or the permits. That is where the next deals are.